Construction project; advance notice of the establishment of a construction site
As a rule, construction sites must be notified in advance to the responsible trade supervisory office or mining authority in the form of an advance notice.
Description
The advance construction site notice must be prepared by the client or a commissioned third party (e.g. architect).
It must contain at least the following information:
- Location of the construction site
- Name and address of the client
- Type of construction project
- Name and address of the third party responsible instead of the client
- Name and address of the coordinator
- Estimated start and duration of the work
- the expected maximum number of employees on the construction site
- Number of employers and contractors without employees expected to work on the construction site
- Details of employers and contractors without employees already selected
Online service
Baustelle - Vorankündigung online
Description
Before setting up a construction site, you can send the responsible trade supervisory office or the responsible mining office the advance notice in accordance with § 2 of the Construction Site Ordinance online.
Use this service online
- Baustelle - Vorankündigung online
Before setting up a construction site, you can send the responsible trade supervisory office or the responsible mining office the advance notice in accordance with § 2 of the Construction Site Ordinance online.
Trust level
The level of trust for this online service is not defined (Trust Level undefined).
further information on the level of trust for online services
Contact person
Regierung von Oberbayern - Gewerbeaufsichtsamt – Dezernat G21 – Bauarbeiterschutz, Asbestsanierung
Address
address
postal address
80534 München
Opening hours
Mo 08:00 Uhr - 16:00 Uhr
Di 08:00 Uhr - 16:00 Uhr
Mi 08:00 Uhr - 16:00 Uhr
Do 08:00 Uhr - 16:00 Uhr
Fr 08:00 Uhr - 14:00 Uhr
Wegen der Außendiensttätigkeit der Mitarbeiter bitten wir für Besuche im Amt einen Termin zu vereinbaren.
Contact
E-Mail: gewerbeaufsichtsamt@reg-ob.bayern.de
Sonstiges: https://www.bayernportal.de/dokumente/behoerde/8318265582385Weiterführende Informationen im BayernPortal
Telefon Festnetz: +49 89 2176-1
Fax: +49 89 2176-3102
Internet
Regierung von Oberbayern - Sachgebiet 26 - Bergamt Südbayern
Address
address
postal address
80534 München
Opening hours
Mo 08:00 Uhr - 16:00 Uhr
Di 08:00 Uhr - 16:00 Uhr
Mi 08:00 Uhr - 16:00 Uhr
Do 08:00 Uhr - 16:00 Uhr
Fr 08:00 Uhr - 14:00 Uhr
und nach Vereinbarung
Contact
E-Mail: bergamt@reg-ob.bayern.de
Sonstiges: https://www.bayernportal.de/dokumente/behoerde/154301803680Weiterführende Informationen im BayernPortal
Telefon Festnetz: +49 89 2176-0
Fax: +49 89 2176-2914
Internet
Required documents
- health and safety plan, if applicable
Prerequisites
If you want to set up a construction site and it fulfills the following requirements, you must submit a construction site advance notice to the trade supervisory office or mining authority responsible for the location of the construction site. The mining authority is responsible, among other things, if the construction project is subject to mining supervision or if it involves underground cavity construction (tunnel, pressing, etc.).
Requirements for the submission of a construction site advance notice:
- Expected duration of more than 30 working days and number of employees working at the same time more than 20
or - Scope of work expected to exceed 500 person days (e.g. if five employees will be working for more than 100 days)
Basis for legal action
Procedure
The advance notice must be sent to the trade supervisory office or mining authority responsible for the location of the construction site.
Deadlines
The advance notice must be sent to the trade supervisory office or mining authority responsible for the location of the construction site at least two weeks before the construction site is set up.
Notes (specifics)
The advance notice must be visibly displayed on the construction site.
The advance notice must be adapted in the event of significant changes.
A coordinator must be appointed for construction sites where employees of several employers are working - regardless of whether they are working simultaneously or consecutively.
In accordance with the Construction Site Ordinance, it must be checked whether a health and safety plan must be drawn up before the construction site is set up.
Further Information
Area of validity
Bavaria
Official approval
Officially approved by Bayerisches Staatsministerium für Familie, Arbeit und Soziales (Bavarian Bavarian State Ministry for Family, Labour and Social Affairs) on 18.09.2025
Keywords
Baustellenanzeige, Sicherheits- und Gesundheitsschutzkoordinator, SiGeKo