Excavation; application for an excavation permit

    You generally require an excavation permit to carry out an excavation. This does not apply to smaller excavations in particular.

    Description

    An excavation permit grants you the right to carry out an excavation for projects requiring approval. In particular, excavations with a maximum base area of 500 m² and a maximum depth of 2 m are not subject to approval. Approval is therefore only not required if both dimensions are not exceeded.

    Excavation in connection with a building project

    If the excavation takes place as part of a building project, you do not need to apply for an excavation permit.

    Excavation not requiring a permit

    If the excavation does not require a permit, you do not need to apply for an excavation permit. You would not be granted such a permit.

    Consequences of not having the required excavation permit

    If you intentionally or negligently carry out an excavation without the required excavation permit, this constitutes an administrative offense. You can be fined up to €500,000 for this.

    Online service

    Bauantrag online

    ID: L100042_80267.-104732

    Description

    You can submit a building application, excavation application, change application and documents for the permit exemption procedure or for an excavation without a procedure online.

    Use this service online

    • Bauantrag online

      You can submit a building application, excavation application, change application and documents for the permit exemption procedure or for an excavation without a procedure online.

    Trust level

    The level of trust for this online service is not defined (Trust Level undefined).

    further information on the level of trust for online services

    Language

    Deutsch

    Sprache: de

    Englisch

    Sprache: en

    Sprachbezeichnung nativ:

    English

    Contact person

    Landratsamt Kulmbach - 33 Baurecht (Bauleitplanung, Bauordnung und Denkmalpflege)

    Address

    address

    Konrad-Adenauer-Straße 5

    95326 Kulmbach

    Save contact

    PO box address

    Post office box 1660

    95307 Kulmbach

    Opening hours

    Mo 07:45 Uhr - 15:00 Uhr

    Di 07:45 Uhr - 15:00 Uhr

    Mi 07:45 Uhr - 12:30 Uhr

    Do 07:45 Uhr - 17:30 Uhr

    Fr 07:45 Uhr - 12:30 Uhr


    Das Landratsamt Kulmbach und die zugehörigen Nebengebäude sind nur nach vorheriger Terminvereinbarung für Besucher zugänglich. Die Terminvergabe erfolgt telefonisch, per E-Mail, schriftlich oder über die Online-Terminvergabe.

    Contact

    Sonstiges: https://www.bayernportal.de/dokumente/behoerde/724193586617Weiterführende Informationen im BayernPortal

    Telefon Festnetz: +49 9221 707-0

    Fax: +49 9221 707-240

    Language version

    Deutsch

    Sprache: de

    Englisch

    Sprache: en

    Sprachbezeichnung nativ:

    English

    Required documents

    • current cadastral map extract
    • Site plan

      (M 1 : 1,000 or 1 : 5,000)

    • Construction drawings
    • Building description (form see under "Forms")
    • any supporting documentation

      Depending on the excavation applied for, further documents may be required. This is particularly the case if an environmental impact assessment is to be carried out.

    Prerequisites

    The excavation permit applied for will only be granted if the project is subject to approval. Furthermore, the excavation must not conflict with any public law regulations that are to be examined in the approval procedure.

    If you do not receive the excavation permit you have applied for, you can file an administrative lawsuit. This must be directed at the granting of the requested excavation permit.

    An objection is not possible.

    Procedure

    Procedure with or without an environmental impact assessment

    The procedure depends in particular on whether or not an environmental impact assessment is to be carried out. The lower excavation authority carries out such an assessment if you apply for an excavation requiring approval with an excavation area of more than 10 hectares. This also applies to excavations with an excavation area of more than one hectare in a protected area, a national park or a nature reserve. If the excavation area of more than one hectare is located in a biotope, the lower excavation authority also carries out an environmental impact assessment.

    The lower excavation authority must be involved in the environmental impact assessment:

    • the authorities whose environmental responsibilities are affected by the project, and
    • the public.

    It is not necessary to involve the neighbors themselves, as they have the opportunity to comment as part of the environmental impact assessment.

    However, if none of the above-mentioned cases apply, the lower excavation authority will not carry out an environmental impact assessment. For you, this means that you must first submit the excavation plan to the neighbors of the excavation site for approval before submitting it. Any consent must be given in writing.

    Written submission
    • Submit the excavation application with the required documents to the responsible lower excavation authority (district offices and independent cities), if necessary after involving the neighbors.
    • Submit the application in triplicate using the forms provided.
    • An oral application is not possible.
    • The lower excavation authority will decide on the application, if necessary after carrying out an environmental impact assessment.
    • If the lower excavation authority is not itself a municipality, it will involve the municipality.
    Digital submission

    Digital submission of excavation applications is not yet possible throughout Bavaria. When a location is selected, the link to the online procedure is displayed if it is already offered.

    • The excavation application can be submitted digitally using the online assistant, if necessary after involving the neighbors.
    • The predefined forms are replaced by the queries in the online assistant.
    • The excavation plan is uploaded to the online assistant in electronic form (files in PDF format).
    • Signatures are replaced by authentication using the "BayernID" user account or "My company account".

    Deadlines

    none

    Processing time

    The processing time depends on the scope and complexity of the project, the current workload of the authority and whether an environmental impact assessment has to be carried out.

    Costs

    The fees for an excavation permit depend on the quantity of usable excavated material.

    • For sand and gravel pits, quarries and similar excavations for the extraction of excavated material for projects with recyclable excavated material up to 50,000 m³ EUR 100 plus EUR 25 per 1,000 m³ or part thereof
    • For sand and gravel pits, quarries and similar excavations for the extraction of excavated material for projects with usable excavated material over 50,000 m³ up to 500,000 m³ EUR 1,350 plus EUR 55 for every 10,000 m³ or part thereof in excess of 50,000 m³
    • For sand and gravel pits, quarries and similar excavations for the extraction of excavated material for projects with usable excavated material in excess of 500,000 m³ EUR 3,825 plus EUR 110 per 500,000 m³ in excess of 50,000 m³ or part thereof
    • EUR 50 to EUR 2,000 for other independent excavations

    If an environmental impact assessment is to be carried out, the fee is increased by 40 %.

    Notes (specifics)

    For excavations requiring approval, apply for the excavation permit and wait until you have been granted it before you start work.

    Area of validity

    Bavaria

    Official approval

    Officially approved by Bayerisches Staatsministerium für Wohnen, Bau und Verkehr (Bavarian State Ministry of Housing, Building and Transport) on 17.11.2025

    Information for Kulmbach: Supplement: Landratsamt Kulmbach

    Officially approved by Landratsamt Kulmbach on 03.07.2025

    Keywords

    Abgrabungsantrag, Abgrabungserlaubnis, Abgrabungsgenehmigung, Abgrabungsgesetz, Abgrabungsrecht, Kiesabbau, Sandabbau

    Language version

    Deutsch

    Sprache: de

    Englisch

    Sprache: en

    Sprachbezeichnung nativ:

    English