Building project; application for a partial building permit

    You can apply for a partial building permit if you have submitted a building application but have not yet received a building permit. This allows you to obtain permits for individual construction phases in advance.

    Description

    You may only start work on your building project once planning permission has been granted. This can take longer, especially for larger projects. With a partial building permit, you can start individual sections of the building project in advance. However, this only applies to the section for which you have received partial building permission.

    The part of your building project that is already covered by the partial building permit is no longer decided as part of the building permit.

    Information for Bad Tölz-Wolfratshausen: Supplement: Landratsamt Bad Tölz-Wolfratshausen

    Please give priority to using the online service arranged above via the "Apply for partial building permit online" button.

    You will also find the following documents in the Forms section:

    • Information sheet - Requirements for the content of an outdoor facilities plan
    • Information sheet - Requirements for acoustic reports
    • Description of commercial operations (for the building application)
    • Supplementary sheet - Description for agricultural businesses (for the building application)
    • Acceptance of clearance area consent
    • Acceptance of clearance areas - Explanation
    • Confirmation of compliance with the list of criteria - Explanation for completing the form
    • Confirmation that the construction complies with the fire protection certificate
    • Declaration on rainwater disposal in the building inspection procedure
    • Declaration of obligation to dismantle in accordance with Section 35 (5) sentence 2 BauGB
    • Declaration of obligation to dismantle in accordance with § 246 Para. 13 S. 4 or Para. 14 S. 7 BauGB
    • Technical connection conditions for fire alarm systems in the district (TAB)
    • Notification of temporary buildings
    • Declaration of groundwater impact in the building supervisory procedure (supplement to the building description)
    • Annex to the building permit application
    • Application for deviation, exemption, exception
    • Application for building permit, excavation permit, preliminary decision, permit exemption procedure - Leaflet on species protection on buildings
    • Building description
    • Description of the restaurant business
    • Proof of authorization to submit building documents in accordance with Art. 61 Bayer. Building Regulations (BayBO)

    Under the further links you will find the page reference to the "Building application procedure".

    Online service

    Teilbaugenehmigung online beantragen

    ID: L100042_50316.-73343

    Description

    You can apply for a partial building permit or a partial excavation permit online.

    Use this service online

    Trust level

    The level of trust for this online service is not defined (Trust Level undefined).

    further information on the level of trust for online services

    Language

    Deutsch

    Sprache: de

    Englisch

    Sprache: en

    Sprachbezeichnung nativ:

    English

    Contact person

    Landratsamt Bad Tölz-Wolfratshausen - Sachgebiet 22 - Kreisbauamt Verwaltung

    Address

    address

    Prof.-Max-Lange-Platz 1

    83646 Bad Tölz

    Save contact

    postal address

    Prof.-Max-Lange-Platz 1

    83646 Bad Tölz

    Opening hours

    Mo 7:30 Uhr - 12:00 Uhr und 13:30 Uhr - 18:00 Uhr

    Di 7:30 Uhr - 12:00 Uhr

    Mi 7:30 Uhr - 12:00 Uhr

    Do 7:30 Uhr - 12:00 Uhr

    Fr 7:30 Uhr - 12:00 Uhr


    Bitte vereinbaren Sie für die persönliche Vorsprache telefonisch oder per E-Mail einen Termin.

    Für Anliegen in der Kfz-Zulassung / Führerscheinstelle steht ihnen unsere Online Terminvereinbarung zur Verfügung.

    Contact

    E-Mail: kreisbauamt@lra-toelz.de

    Sonstiges: https://www.bayernportal.de/dokumente/behoerde/1944548681494Weiterführende Informationen im BayernPortal

    Telefon Festnetz: +49 8041 505-555

    Fax: +49 8041 505-394

    Language version

    Deutsch

    Sprache: de

    Englisch

    Sprache: en

    Sprachbezeichnung nativ:

    English

    Landratsamt Bad Tölz-Wolfratshausen - Sachgebiet 24 - Kreisbauamt Technik

    Address

    address

    Prof.-Max-Lange-Platz 1

    83646 Bad Tölz

    Save contact

    postal address

    Prof.-Max-Lange-Platz 1

    83646 Bad Tölz

    Opening hours

    Mo 7:30 Uhr - 12:00 Uhr und 13:30 Uhr - 18:00 Uhr

    Di 7:30 Uhr - 12:00 Uhr

    Mi 7:30 Uhr - 12:00 Uhr

    Do 7:30 Uhr - 12:00 Uhr

    Fr 7:30 Uhr - 12:00 Uhr


    Bitte vereinbaren Sie für die persönliche Vorsprache telefonisch oder per E-Mail einen Termin.

    Für Anliegen in der Kfz-Zulassung / Führerscheinstelle steht ihnen unsere Online Terminvereinbarung zur Verfügung.

    Contact

    E-Mail: kreisbauamt@lra-toelz.de

    Sonstiges: https://www.bayernportal.de/dokumente/behoerde/1978104235494Weiterführende Informationen im BayernPortal

    Telefon Festnetz: +49 8041 505-555

    Fax: +49 8041 505-394

    Language version

    Deutsch

    Sprache: de

    Englisch

    Sprache: en

    Sprachbezeichnung nativ:

    English

    Required documents

    • Construction drawings
    • Building description (form see under "Forms")
    • Cost calculation

      For fee purposes, you must provide the estimated construction costs of the partial construction measures.

    • Building specification

    Prerequisites

    You must first submit a building application. Only then can you apply for a partial building permit for part of the project.

    The partial building permit applied for will only be granted if the project is subject to approval. Furthermore, the part of the project must not conflict with any public law regulations and the lower building supervisory authority must determine that the overall building project is generally permissible. The granting of the partial building permit is at the discretion of the lower building supervisory authority.

    If you do not receive the partial building permit you have applied for, you can take legal action in an administrative court. This must be directed at the granting of the partial building permit applied for. However, it is at the discretion of the lower building supervisory authority to grant the partial building permit. In principle, you do not have a legal claim to the granting of a partial building permit even if there are no public law regulations that conflict with the part of the project for which the partial building permit is being applied for.

    An objection is not possible.

    Procedure

    Written submission

    First of all, please note that in the case of building applications for the construction and alteration of buildings, the building documents must be prepared by an authorized draftsman (architect, civil engineer; for smaller building projects, especially detached and semi-detached houses, also master craftsmen in the building and carpentry trades and state-certified technicians in the field of construction technology). This also applies to the building documents for the application for partial building permission.

    • After submitting your building application, submit the partial building application with the required documents in writing to the lower building supervisory authority (district offices, independent cities, large district towns and certain larger municipalities) in whose area the building plot is located.
    • A specific form is not required. An oral application is not possible.
    • The application must be signed by the building owner and the authorized designer.
    • The lower building supervisory authority examines the application and decides on it.
    • Before making a decision, the lower building supervisory authority must involve the authorities whose involvement or consultation is required by law for the decision on the building application or without whose opinion the approvability of the building application cannot be assessed (e.g. the lower immission control authority, the lower water authority or the road traffic authority). However, this only applies if these authorities have not already commented on the overall building application. The municipal consent must already be obtained before the partial building permit is issued if it is required under building planning law.
    Digital submission

    Digital submission of applications for partial building permits is not yet possible throughout Bavaria. When selecting a location, the link to the online procedure is displayed, if it is already offered.

    • The application for partial building permission can be submitted digitally to the lower building supervisory authority using the online assistant.
    • The building documents are uploaded to the online assistant in electronic form (files in PDF format). The signatures of the client and the authorized designer are replaced by authentication using the "BayernID" user account or "My company account".
    • In the case of applications for partial building permits where the building documents must be prepared by an authorized designer, the latter must authenticate himself and submit the application on behalf of the client.

    Deadlines

    The partial building permit must be applied for before the building permit is issued.

    Processing time

    The processing time depends on the scope and complexity of the application, the number of agencies involved and the current workload of the authority.

    Costs

    The fees for a partial building permit amount to between 1 per thousand and 4 per thousand of the construction costs, depending on the type of construction project and the type of approval procedure. The fee is offset against the subsequent building permit fee.

    Notes (specifics)

    A partial building permit can be particularly useful for excavating a building pit, laying the foundations and constructing the basement. A granted partial building permit also contains the statement that the overall project is basically approvable. In individual cases, however, you may not receive the building permit you applied for at a later date.

    Further Information

    Information for Bad Tölz-Wolfratshausen: Supplement: Landratsamt Bad Tölz-Wolfratshausen

    Area of validity

    Bavaria

    Official approval

    Officially approved by Bayerisches Staatsministerium für Wohnen, Bau und Verkehr (Bavarian State Ministry of Housing, Building and Transport) on 17.11.2025

    Information for Bad Tölz-Wolfratshausen: Supplement: Landratsamt Bad Tölz-Wolfratshausen

    Officially approved by Landratsamt Bad Tölz-Wolfratshausen on 09.01.2026

    Keywords

    Abschnittsbaugenehmigung, Bauaufsicht, Erleichterung, Genehmigungsverfahren, Teilprüfung

    Language version

    Deutsch

    Sprache: de

    Englisch

    Sprache: en

    Sprachbezeichnung nativ:

    English