Construction site: Issuing - of construction site orders under traffic law
Work sites that have an impact on road traffic, such as
* Excavations in the road area
* road construction
* Work in the side area
* Erection of scaffolding
Description
Work sites that have an impact on road traffic, such as
- Excavations in the road
- road construction
- Work in the side area
- Erection of scaffolding
must be secured.
Before starting the work, the contractor must obtain instructions from the competent authority (including a traffic sign plan) on how the work site is to be cordoned off and marked and how traffic is to be restricted, regulated and routed.
Online services
There is currently no online service available for this location.
Competent office
Responsibility lies with the district, the independent city, the large independent city and the independent municipality.
For municipal roads, responsibility can be transferred to the respective municipality, joint municipality and town.
If the approval authority is located within Lower Saxony, the Lower Saxony State Authority for Road Construction and Transport (NLStBV) as the road construction authority for the
- Federal highways,
- federal and state roads and
- the district roads under the technical administration of the state (especially with regard to construction sites and bridge structures)
by the responsible body.
Contact point
Responsibility lies with the district, the independent city, the large independent city and the independent municipality.
For municipal roads, responsibility can be transferred to the respective municipality, joint municipality and town.
If the approval authority is located within Lower Saxony, the Lower Saxony State Authority for Road Construction and Transport (NLStBV) as the road construction authority for the
- Federal highways,
- federal and state roads and
- the district roads under the technical administration of the state (especially with regard to construction sites and bridge structures)
by the responsible body.
Contact person
Unfortunately, no contact persons were found for District Verden (Lower Saxony). Please check the service description above for information on how to find the responsible contact person.
Forms
not specified
Prerequisites
The traffic law measures required to secure the work site must always be checked on a case-by-case basis. The contractor and the traffic authority have access to the guidelines for securing road works (RSA) as well as standard plans for all possible safety measures.
Basis for legal action
Legal remedy
not specified
Procedure
The contractor must check which road safety measures are necessary and appropriate during the planning phase of the work site based on the specific local conditions. A written application must then be submitted to the traffic authority for the traffic safety measures to be ordered.
The traffic authority examines the application and the documents submitted and consults the authorities to be involved (police and road construction authority). If necessary, a site inspection is carried out with all parties involved in order to coordinate the necessary measures on site. The necessary measures are then ordered by the traffic authority to be carried out by the contractor.
Deadlines
Deadlines may have to be observed. Please contact the responsible office.
Application deadline: 2 weeks (The application must be submitted in good time, at least two weeks before the start of the construction work.)
Processing time
not specified
Costs
Fee from 10,20 EUR to 767,00 EUR
Notes (specifics)
Roadworks information for Lower Saxony can be found on the Internet on the websites of the Federal Ministry of Transport, Building and Urban Development and the Traffic Management Center.
Information can also be obtained from the traffic authorities of the municipalities and the road and highway maintenance depots of the Lower Saxony State Authority for Road Construction and Traffic.
Unterstützende Institutionen
not specified
Welche Dokumente resultieren aus dieser Leistung?
not specified
Area of validity
Lower Saxony
Official approval
Officially approved by Federal Ministry for Digital and Economic Affairs and Transport
Keywords