Construction: Deviation/Exception/Exemption

    Description

    If deviations are to be made from the provisions of building planning law or building regulations, an application for exception, exemption or deviation may be submitted. The building supervisory authority decides on the application, which must be justified.

    In building application procedures, a requested deviation from the provisions of building regulations or an exception or exemption from planning regulations is decided with the building application.

    An independent application for derogation is only possible for structures according to § 73 HBO. This is not possible for projects in the planned area that do not require approval (§ 63 HBO). In such cases, the derogation, exception or exemption must be decided in an authorisation procedure.
     

    Online services

    There is currently no online service available for this location.

    Contact point

    Further information can be obtained from the building supervisory authority (district / district-free city / special status city).

    Contact person

    Kreisverwaltung Darmstadt-Dieburg - Bauaufsicht, Denkmalschutz, Immissionsschutz

    Address

    address

    Jägertorstraße 207

    64289 Darmstadt

    Save contact

    Elevator available

    Wheelchair access

    Contact

    Internet

    Version

    Technisch geändert on 21.01.2026

    Language version

    de

    Sprache: de

    Required documents

    • Application for deviation / exception / exemption according to § 73 Hessische Bauordnung - HBO - / § 31 Baugesetzbuch - BauGB - with justification and explanation of the compensation measure
    • Property plan (site plan/excerpt from the property map) not older than 12 months and with measured entry of the project
    • Ev. further required documents can be obtained from the building supervisory authority
    • if neighbouring rights are affected by the deviation / exception / exemption, the neighbourhood will be involved. Prior consent from neighbours can significantly speed up the procedure.
       

    Costs

    For deviations from the building regulations, a fee framework of 50.00 Euro - 10,000.00 Euro is provided; for planning exceptions a fee framework of 40.00 Euro - 1.300,00 Euro, for exemptions 40.00 Euro - 20.000,00 Euro. For exemptions with a volume of more than 1,000 m³ for special constructions, the fee framework is 20,000.00 euros - 50,000.00 euros.

    Area of validity

    Hesse

    Version

    Technisch erstellt on 21.06.2010

    Technisch geändert on 08.07.2024

    Keywords

    Baugenehmigung, Behörde, Abweichung, Bau, Ausnahme, Bauen, Bauantrag, Bauplanung, Befreiung, Bebauungsplan

    Language version

    Deutsch

    Sprache: de

    Technisch erstellt on 07.06.2017

    Technisch geändert on 14.05.2025

    Englisch

    Sprache: en

    Sprachbezeichnung nativ:

    English

    Technisch erstellt on 07.07.2021

    Technisch geändert on 26.11.2019