Construction site layout for road works

    If you want to set up a construction site as a company, you must comply with the official regulations.

    Description

    The contractor must already check which traffic safety measures are necessary and appropriate during the planning phase of the work site based on the local conditions. A written application must then be submitted to the traffic authority for the traffic safety measures to be ordered.

    The traffic authority examines the application and the documents submitted and consults the authorities to be involved (police and road construction authority). If necessary, a site inspection is carried out with all parties involved in order to coordinate the necessary measures on site. The necessary measures are then ordered by the traffic authority to be carried out by the contractor.

    Online services

    There is currently no online service available for this location.

    Contact point

    The road traffic authorities are responsible for issuing the order. These are

    • for federal, state, district and municipal roads (all roads with the exception of freeways) in independent cities and district municipalities with more than 50,000 inhabitants, the mayors,
    • the mayors for state, district and municipal roads in municipalities with more than 7,500 inhabitants and for district and municipal roads in municipalities with up to 7,500 inhabitants
    • and for the rest (federal roads in the area of municipalities belonging to districts with up to 50,000 inhabitants and state roads in the area of municipalities with up to 7,500 inhabitants) the district councillors.
    • The road traffic authority for the highways in Hesse is Autobahn GmbH des Bundes (AdB)

    Contact person

    Kreisverwaltung Darmstadt-Dieburg - Verkehr

    Address

    address

    Jägertorstraße 207

    64289 Darmstadt

    Save contact

    Elevator available

    Wheelchair access

    address

    Albinistraße 23

    64807 Dieburg

    Save contact

    Elevator available

    Wheelchair access

    Opening hours

    Contact

    Internet

    Version

    Technisch geändert on 19.01.2026

    Language version

    de

    Sprache: de

    Required documents

    • Written application
    • Proof of the required specialist knowledge in accordance with the leaflet on general conditions for the specialist knowledge required for traffic safety at road works (MVAS)
    • Traffic sign plan (either standard plan of the RSA or individual)
    • Detour plan, if applicable

    Prerequisites

    The traffic measures required to make the work site safe must always be checked on a case-by-case basis. The contractor and the road traffic authority have access to the guidelines for securing work sites on roads (RSA) as well as standard plans for all possible safety measures.

    Those responsible for traffic safety and the operation and troubleshooting of any signal systems must provide evidence of the necessary specialist knowledge in accordance with the information sheet on the general conditions for the specialist knowledge required for traffic safety at road works (MVAS). The ordering authority may allow exceptions to this rule for work with a minor impact on traffic.

    Procedure

    The contractor must already check which traffic safety measures are necessary and appropriate during the planning phase of the work site based on the local conditions. A written application must then be submitted to the traffic authority for the traffic safety measures to be ordered.
    The traffic authority examines the application and the documents submitted and consults the authorities to be involved (police and road construction authority). If necessary, a site inspection is carried out with all parties involved in order to coordinate the necessary measures on site. The necessary measures are then ordered by the traffic authority to be carried out by the contractor.

    Deadlines

    Application deadline: 2 weeks (Before the start of construction work.)

    Costs

    The amount of the fee depends on the type and scope of the order to be issued and is set out in the Annex to Section 1 - Tariff of fees for road traffic measures of the scale of fees for road traffic measures.

    Fee from 10,20 EUR to 767,00 EUR

    Area of validity

    Hesse

    Official approval

    Officially approved by Hessian Ministry of Economics, Energy, Transport and Housing on 21.02.2024

    Version

    Technisch erstellt on 07.11.2008

    Technisch geändert on 28.08.2024

    Keywords

    Bauzaun, Baustellengenehmigung, Straßenbau, Kfz, Gerüst, Nutzung öffentlicher Verkehrsflächen, Baustellenanordnung, Ausnahmegenehmigung, Verkehrssicherung, Straßenerhaltung

    Language version

    Deutsch

    Sprache: de

    Technisch erstellt on 07.06.2017

    Technisch geändert on 14.05.2025

    Englisch

    Sprache: en

    Sprachbezeichnung nativ:

    English

    Technisch erstellt on 07.07.2021

    Technisch geändert on 26.11.2019