Applying for a building permit

    As a rule, you require a building permit for the construction, modification and change of use of (structural) facilities.

    Description

    As a rule, you require a building permit for the construction, erection, installation, modification, change of use, demolition and removal of (structural) installations or parts thereof.

    For special buildings (e.g. high-rise buildings), planning permission is granted in the conventional planning permission procedure.

    For other construction projects requiring approval, planning permission is granted in the simplified planning permission procedure.

    You can apply for a building permit by submitting a building application together with the necessary documents digitally in the building portal or in analog form.


    You may only start building once you have received the building permit.

    The construction site sign must be visible from the public road.

    The building permit expires if you do not start construction work within 3 years of the permit being issued or if construction work has been interrupted for one year after this period. The period can be extended by up to 2 years in each case with a written application.

    Information for Rüsselsheim am Main: Baugenehmigung (Bauantrag)

    Wer in Rüsselsheim am Main eine nach der Hessischen Bauordnung genehmigungspflichtige Baumaßnahme durchführen will, benötigt hierfür eine Baugenehmigung. Der Bauantrag sollte frühzeitig vor dem geplanten Baubeginn gestellt werden, da ohne Genehmigung mit der Ausführung nicht begonnen werden darf.

    Online service

    Zum Quick-Check Bauantrag

    ID: L100001_425577244

    Use this service online

    Trust level

    The level of trust for this online service is not defined (Trust Level undefined).

    further information on the level of trust for online services

    Version

    Technisch erstellt on 18.06.2025

    Technisch geändert on 16.12.2025

    Language

    Deutsch

    Sprache: de

    Technisch erstellt on 07.06.2017

    Technisch geändert on 14.05.2025

    Contact point

    To the lower building supervisory authority (building supervisory authorities of the districts, independent cities, special status cities).

    Contact person

    Landkreis Groß-Gerau - Bürgerdienste - Bauaufsicht - Bauordnungs- und Wohnungswesen

    Address

    address

    Wilhelm-Seipp-Straße 4

    64521 Groß-Gerau

    Save contact

    Contact

    telephone: 06152 989-526(Service Telefon für allgemeine Auskünfte: Dienstag, Mittwoch und Donnerstag von 9.00 bis 12.00 Uhr)

    telephone: 06152 989-526(Telefonische Erreichbarkeit der technischen Sachbearbeiter und Verwaltungssachbearbeiter: Dienstag und Donnerstag von 9.00 bis 12.00 Uhr)

    fax: 06152 989-580

    e-mail: bauaufsicht@kreisgg.de

    Internet

    Version

    Technisch geändert on 02.12.2025

    Language version

    de

    Sprache: de

    Required documents

    Information on the required documents and forms can be found under the attached link to building documents.

    Prerequisites

    All required documents and forms have been submitted in full digitally in the construction portal or in analog form. The project does not conflict with any public law regulations.

    An appeal may be lodged against the authority's decision within one month of notification.

    Procedure

    As the building owner, you must submit the building application with the required building documents to the building supervisory authority in whose area the property is located.
    The building supervisory authority will check whether the building documents are complete. If the building application cannot be processed due to missing documents, it may be rejected. Individual building documents can be requested subsequently.
    If the building documents are complete, the building supervisory authority (with the involvement of the municipality and specialist departments) will check whether the building project is contrary to public law regulations. Once all comments have been received and the building application has been reviewed, the building supervisory authority will inform you of its decision digitally via the building portal or in analog form:
    - the building permit is granted,
    - only granted with certain requirements and conditions or
    - the building application is rejected.

    You may only start work on the project once you have received the building permit.

    Deadlines

    A building permit issued is valid for 3 years. If building work is not carried out until a later date, an extension of the building permit must be applied for in writing before the deadline expires. This also applies if construction work has been interrupted for more than one year.

    Processing time

    The duration of the procedure depends on the individual case, in particular on which offices need to be involved and whether all the necessary documents are complete.

    Costs

    With the exception of demolition, the amount of the fees is based on the structural costs of the building. The respective local authorities can set fees that deviate from the list of fees in the administrative cost regulations by means of statutes. Please contact the building supervisory authority responsible for you.

    Information for Rüsselsheim am Main: Baugenehmigung (Bauantrag)

    Gemäß Gebührensatzung der Stadt Rüsselsheim vom 27.06.2019 und Verwaltungskostenverzeichnis Nummer 611 bis 613 und 6145 bis 6171 zur Verwaltungskostenordnung für den Geschäftsbereich des Ministeriums für Wirtschaft, Energie, Verkehr und Wohnen vom 19. November 2012 (Gesetz- und Verordnungsblatt Seite 484, 2013 Seite 44), zuletzt geändert durch Verordnung vom 28. Januar 2020 (Gesetz- und Verordnungsblatt Seite 98).

    Weitere Informationen:

    Bauaufsichtsgebührensatzung

    Notes (specifics)

    Firing systems may only be put into operation after the expert for energy generation systems (e.g. the authorized chimney sweep) has certified that they are safe to use and that the exhaust gases are properly discharged.

    Area of validity

    Hesse

    Official approval

    Officially approved by Hessian Ministry of Economics, Energy, Transport and Housing on 20.02.2026

    Version

    Technisch erstellt on 21.10.2008

    Technisch geändert on 23.02.2026

    Keywords

    Kindergarten, Schools, Kindergartens, High-rise buildings, Office building, Amusement park, Entertainment venues, Restaurants, Building projects requiring approval, Attachments, Building

    Language version

    Deutsch

    Sprache: de

    Technisch erstellt on 07.06.2017

    Technisch geändert on 14.05.2025

    Englisch

    Sprache: en

    Sprachbezeichnung nativ:

    English

    Technisch erstellt on 07.07.2021

    Technisch geändert on 26.11.2019