Obtain approval from the building inspectorate

    Are there any special regulations for the approval of publicly owned construction projects? Do you want to apply for approval for such a construction project?

    Description

    Construction projects under public ownership require the approval of the building supervisory authority instead of a building permit if it is transferred to a federal or state building department under the direction of the design work and the building department is occupied.  

    In certain constellations, the consent requirement may be waived.

    Projects that serve the purpose of national defence must be brought to the attention of the higher building supervisory authority in an appropriate manner before construction begins; there is no inspection by the higher building inspectorate.

    Online services

    There is currently no online service available for this location.

    Competent office

    Lower Building Supervisory Authority (Building Supervisory Authorities of the Districts, Independent Cities and Special Status Cities)

    Contact person

    Kreisverwaltung Darmstadt-Dieburg - Bauaufsicht, Denkmalschutz, Immissionsschutz

    Address

    address

    Jägertorstraße 207

    64289 Darmstadt

    Save contact

    Elevator available

    Wheelchair access

    Contact

    Internet

    Version

    Technisch geändert on 21.01.2026

    Language version

    de

    Sprache: de

    Required documents

    Request for approval and submission of all building documents required for the assessment of the application
     

    Prerequisites

    • The management of the design work is entrusted to a federal or state building department
    • The building department must be staffed
       

    Procedure

    • You fill out the application digitally in the construction portal or analogue and submit it together with the required documents to the responsible building authority
    • The building authority will examine your application and the documents
    • If all the requirements are met, the building authority will give you the go-ahead
       

    Processing time

    A decision on the application for consent must be made within three months of receipt of the complete application documents.

    This period may be extended by up to two months for good cause. If a decision is not taken on the application within the relevant time limit, it shall be deemed to have been granted.

    Costs

    The costs are calculated on the basis of the shell construction sum.

    Area of validity

    Hesse

    Official approval

    Officially approved by Hessian Ministry of Economic Affairs, Energy, Transport and Housing on 12.10.2023

    Version

    Technisch erstellt on 21.10.2008

    Technisch geändert on 27.10.2023

    Keywords

    Bauüberwachung, Baudienststelle, Bauaufsichtliche Zustimmung, Errichtung, Hessische Bauordnung, Bauverfahren, Bauordnung, Bauaufsicht, Anlagen der Landesverteidigung, Vorhaben öffentliche Trägerschaft, Behörde, Zustimmung, Bauamt

    Language version

    Deutsch

    Sprache: de

    Technisch erstellt on 07.06.2017

    Technisch geändert on 14.05.2025

    Englisch

    Sprache: en

    Sprachbezeichnung nativ:

    English

    Technisch erstellt on 07.07.2021

    Technisch geändert on 26.11.2019