Obtain approval from the building inspectorate
Are there any special regulations for the approval of publicly owned construction projects? Do you want to apply for approval for such a construction project?
Description
Construction projects under public ownership require the approval of the building supervisory authority instead of a building permit if it is transferred to a federal or state building department under the direction of the design work and the building department is occupied.
In certain constellations, the consent requirement may be waived.
Projects that serve the purpose of national defence must be brought to the attention of the higher building supervisory authority in an appropriate manner before construction begins; there is no inspection by the higher building inspectorate.
Online services
There is currently no online service available for this location.
Competent office
Lower Building Supervisory Authority (Building Supervisory Authorities of the Districts, Independent Cities and Special Status Cities)
Contact person
Kreisverwaltung Darmstadt-Dieburg - Bauaufsicht, Denkmalschutz, Immissionsschutz
Address
address
Contact
telephone: 06151 881-2341
e-mail: bauaufsicht@ladadi.de
Internet
Required documents
Request for approval and submission of all building documents required for the assessment of the application
Prerequisites
- The management of the design work is entrusted to a federal or state building department
- The building department must be staffed
Basis for legal action
Procedure
- You fill out the application digitally in the construction portal or analogue and submit it together with the required documents to the responsible building authority
- The building authority will examine your application and the documents
- If all the requirements are met, the building authority will give you the go-ahead
Processing time
A decision on the application for consent must be made within three months of receipt of the complete application documents.
This period may be extended by up to two months for good cause. If a decision is not taken on the application within the relevant time limit, it shall be deemed to have been granted.
Costs
The costs are calculated on the basis of the shell construction sum.
Area of validity
Hesse
Official approval
Officially approved by Hessian Ministry of Economic Affairs, Energy, Transport and Housing on 12.10.2023
Keywords
Bauüberwachung, Baudienststelle, Bauaufsichtliche Zustimmung, Errichtung, Hessische Bauordnung, Bauverfahren, Bauordnung, Bauaufsicht, Anlagen der Landesverteidigung, Vorhaben öffentliche Trägerschaft, Behörde, Zustimmung, Bauamt