Submit measurement report on individual measurements of air pollutants at plants for the incineration and co-incineration of waste

    If you operate a waste incineration plant or a combustion plant in which you co-incinerate waste, you must have the pollutant emissions determined regularly by individual measurements.

    Description

    If you are the operator of a waste incineration or waste co-incineration plant, you must have the air pollutant emissions determined at regular intervals by means of individual measurements.

    You must have the measurements carried out by an accredited measuring institute or an expert.

    In Hesse, the measurements must be carried out by a notified body.

    You can find these under:

    Information for Hesse: Messbericht über Einzelmessungen von Luftschadstoffen bei Anlagen für die Verbrennung und die Mitverbrennung von Abfällen vorlegen

    In Hesse, the measurements must be carried out by a notified body.

    You can find these under:

    Competent office

    The environmental departments of the regional councils are responsible.

    Contact point

    Please contact the environmental department of the regional council responsible for you.

    Contact person

    Regierungspräsidium Kassel - Dezernat 33.2 - Immissionsschutz und Energiewirtschaft

    Address

    address

    Hubertusweg 19

    36251 Bad Hersfeld

    Save contact

    Elevator available

    Wheelchair access

    Opening hours

    Sie können uns täglich persönlich und telefonisch erreichen:

    montags - donnerstags 08:00 - 16:30 Uhr

    freitags 08:00 - 15:00 Uhr

    Contact

    Internet

    Version

    Technisch geändert on 09.04.2025

    Language version

    de

    Sprache: de

    Required documents

    Complete measurement report with details of:

    • Measurement planning
    • measurement result
    • Measurement methods used
    • Operating conditions that are important for assessing the measurement results

    Prerequisites

    • You are the operator of a waste incineration or waste co-incineration plant that requires a permit.
    • You have newly constructed or significantly modified your plant.
    • You have put your plant into operation.

    The administrative service is a real act against which no legal remedy is possible.

    Procedure

    • You contact an accredited measuring institute or an expert, provide the necessary information for the measurement and arrange a measurement date.
    • The measuring institute or expert then confirms the measurement plan for you and reports it to the authority responsible for you together with the measurement date.
    • On the measurement date, the measuring institute or expert determines the emission values and compares them with the legally prescribed emission limit values for your system.
    • Once the measurement has been completed, you will receive a measurement report from the measuring institute or expert.
    • You must check the measurement report and send it together with the measurement planning, the result of each individual measurement, the measurement method used and the operating conditions during the measurement to the immission control authority responsible for you.
    • You will receive confirmation from the authority that your measurement report has been received.

    Deadlines

    The measurement report must be submitted to the responsible authority together with all documents 8 weeks after the measurements.

    If your system has been newly installed or significantly modified, you must have the measurements carried out every 2 months in the first year after commissioning and then regularly every 6 months thereafter.

    Processing time

    There is no statutory processing time.

    Costs

    In Hesse, fees for the official inspection of measurement reports are charged on a time basis.

    Fee free of charge

    Information for Hesse: Messbericht über Einzelmessungen von Luftschadstoffen bei Anlagen für die Verbrennung und die Mitverbrennung von Abfällen vorlegen

    In Hesse, fees for the official inspection of measurement reports are charged on a time basis.

    Notes (specifics)

    • The content of the measurement report must comply with Annex A of Guideline VDI 4220 Sheet 2 (2018 edition).
    • If you do not have the measurements carried out, do not have them carried out in the prescribed manner or do not have them carried out on time, you are committing an administrative offense that can be punished with a fine.

    Further Information

    Area of validity

    Hesse

    Official approval

    Officially approved by Hessian Ministry of Agriculture and Environment, Viticulture, Forestry, Hunting and Homeland on 11.03.2025

    Version

    Technisch erstellt on 22.05.2024

    Technisch geändert on 14.03.2025

    Keywords

    Quecksilber, Emissionsbericht, Müllverbrennungsanlage, Immissionsschutzgesetz, Pyrolyse, Schadstoffmessung, Emissionsmessung, Großfeuerungsanlage, genehmigungsbedürftige Anlage, Emissionsmessbericht, VDI 4220, ReSyMeSa, 17 BImSchV, Abfallverbrennungsanlage, Messstelle, Abfallmitverbrennungsanlage, Luftschadstoffe, LAI-Mustermessbericht, TA Luft

    Language version

    Deutsch

    Sprache: de

    Technisch erstellt on 07.06.2017

    Technisch geändert on 14.05.2025

    Englisch

    Sprache: en

    Sprachbezeichnung nativ:

    English

    Technisch erstellt on 07.07.2021

    Technisch geändert on 26.11.2019