Applying for a partial building permit for the construction of a building structure

    Description

    If a building application has been submitted, the start of construction work for the excavation pit and for individual parts or construction phases of the project can be approved on application before the building permit is issued (partial building permit). The subject of the partial building permit is on the one hand - as an enacting part - the release of the preparatory construction measures. On the other hand, the partial building permit - as a declaratory part - contains a so-called "provisional positive overall judgment" with regard to the basic approvability of the overall project.

    The partial building permit expires if you do not start construction work within three years of the permit being granted or if construction work has been interrupted for one year after this period. The period can be extended by up to two years in each case, even several times, with a written application.

    Online services

    There is currently no online service available for this location.

    Competent office

    Lower building supervisory authority (building supervisory authorities of the districts, independent cities and special status cities).

    Contact person

    Kreisverwaltung Darmstadt-Dieburg - Bauaufsicht, Denkmalschutz, Immissionsschutz

    Address

    address

    Jägertorstraße 207

    64289 Darmstadt

    Save contact

    Elevator available

    Wheelchair access

    Contact

    Internet

    Version

    Technisch geändert on 21.01.2026

    Language version

    de

    Sprache: de

    Required documents

    A partial building permit can only be issued upon application. This must be submitted digitally in the construction portal or in analog form. All documents required for the assessment must be enclosed with the application. As the scope of the required documents depends on the scope of the construction work to be approved, it is not possible to make general statements in this regard. These must be determined in consultation with the locally responsible lower building supervisory authority.

    Prerequisites

    All required documents and forms have been submitted in full. The project does not conflict with any public law regulations.

    An appeal may be lodged against the authority's decision within one month of notification.

    Procedure

    • You complete the application digitally in the building portal or in analog form and submit it together with the required documents to the responsible building authority
    • The building authority checks your application and the documents
    • If all requirements are met, the building authority will grant you the permit

    Processing time

    Differs depending on the building inspectorate.

    Costs

    Additional fees corresponding to the scope of the partial building permit may be charged, which are to be offset against the final fees (e.g. for demolition work).: Fee from 65,00 EUR to 410,00 EUR

    Area of validity

    Hesse

    Official approval

    Officially approved by Hessian Ministry of Economics, Energy, Transport and Housing. on 05.10.2023

    Version

    Technisch erstellt on 27.10.2023

    Technisch geändert on 08.07.2024

    Keywords

    Baugrube, Entwässerungsanlagen, Teilbaugenehmigung, Fundamente

    Language version

    Deutsch

    Sprache: de

    Technisch erstellt on 07.06.2017

    Technisch geändert on 14.05.2025

    Englisch

    Sprache: en

    Sprachbezeichnung nativ:

    English

    Technisch erstellt on 07.07.2021

    Technisch geändert on 26.11.2019