Show state of construction

    Do you want to inform the lower building supervisory authority of the progress of your building project?

    Description

    The client must notify the lower building supervisory authority of the completion of the shell, the final completion and, if applicable, the commencement of use prior to completion.

    Online services

    There is currently no online service available for this location.

    Competent office

    The lower building supervisory authorities are responsible.

    Contact point

    Please contact the lower building supervisory authority of your district, independent city or special status city.

    Contact person

    Kreisverwaltung Darmstadt-Dieburg - Bauaufsicht, Denkmalschutz, Immissionsschutz

    Address

    address

    Jägertorstraße 207

    64289 Darmstadt

    Save contact

    Elevator available

    Wheelchair access

    Contact

    Internet

    Version

    Technisch geändert on 21.01.2026

    Language version

    de

    Sprache: de

    Required documents

    No documents are required.

    Prerequisites

    There are no prerequisites.

    Procedure

    You fill out the form(s) digitally in the building portal or in analog form and submit it to the responsible lower building supervisory authority.

    Deadlines

    • The completion of the shell of buildings that do not require a building permit and the final completion must be notified to the building supervisory authority at least two weeks in advance, stating the date of completion.
    • The commencement of full or partial premature use must be notified to the building supervisory authority one week in advance.

    Processing time

    There is no fixed processing time, the notification simply has to be submitted.

    Costs

    There are no fees.

    Notes (specifics)

    There are no indications or special features.

    Further Information

    Area of validity

    Hesse

    Official approval

    Officially approved by Hessian Ministry of Economics, Energy, Transport and Housing (HMWEVW) on 27.09.2023

    Version

    Technisch erstellt on 05.10.2023

    Technisch geändert on 08.07.2024

    Keywords

    Baustelle, Abschließende Fertigstellung, Rohbau, Bauzustand, Baugenehmigung

    Language version

    Deutsch

    Sprache: de

    Technisch erstellt on 07.06.2017

    Technisch geändert on 14.05.2025

    Englisch

    Sprache: en

    Sprachbezeichnung nativ:

    English

    Technisch erstellt on 07.07.2021

    Technisch geändert on 26.11.2019