Applying for an extension of the building permit for the construction of an installation

    You can apply for an extension of the building permit for up to two years at a time if you have a valid building permit for the construction of an installation for your building project.

    Description

    The building permit expires if you do not start building work within three years of the permit being granted or if building work has been interrupted for one year.

    The deadline can be extended by up to two years in each case with a written application if the legal requirements have not changed in the meantime and the application has been received by the lower building supervisory authority before the deadline expires. The extension of the building permit is subject to a fee.

    Online services

    There is currently no online service available for this location.

    Competent office

    The lower building supervisory authorities are responsible.

    Contact point

    Please contact the lower building supervisory authority of your district, independent city or special status city.

    Contact person

    Unfortunately, no contact persons were found for Lohra (District Marburg-Biedenkopf, Hesse). Please check the service description above for information on how to find the responsible contact person.

    Required documents

    An informal application is sufficient.

    Prerequisites

    • Valid building permit
    • Application before expiry of the extension period of three years since the building permit was issued
    • the legal requirements have not changed in the meantime

    An appeal may be lodged against the authority's decision within one month of notification.

    Procedure

    • You make the application informally and submit it to the responsible building supervisory authority together with any necessary documents.
    • The building supervisory authority will review your application.
    • If the factual and legal situation has not changed, there is nothing to prevent an extension of up to two years. The extension is subject to a fee.

    Deadlines

    • Application for extension during the term of the building permit, which is three years.
    • The building permit can be extended by up to two years at a time.

    Costs

    At least EUR 100.

    The fee is to be calculated proportionately according to the extent to which the building permit is anticipated by the preliminary decision.
    The respective local authorities can set fees by statute. Please contact the building supervisory authority responsible for you.

    Notes (specifics)

    There are no indications or special features.

    Further Information

    Area of validity

    Hesse

    Official approval

    Officially approved by Hessian Ministry of Economics, Energy, Transport, Housing and Rural Areas on 11.06.2024

    Version

    Technisch erstellt on 04.10.2023

    Technisch geändert on 08.07.2024

    Keywords

    Baugenehmigung, Verlängerung Baugenehmigung

    Language version

    Deutsch

    Sprache: de

    Technisch erstellt on 07.06.2017

    Technisch geändert on 14.05.2025

    Englisch

    Sprache: en

    Sprachbezeichnung nativ:

    English

    Technisch erstellt on 07.07.2021

    Technisch geändert on 26.11.2019