Premature construction of a plant requiring approval in accordance with the BImSchG approval
In a procedure for the granting of a permit for installations requiring a permit, you can submit an application to the competent authority for the early start of the construction of a plant.
Description
If you are seeking approval for the early construction of a facility requiring a permit, you must prove that:
1. a decision in your favour can be expected,
2. there is a public interest or a legitimate interest in the early start of their project, and
3. You undertake to compensate for all damage caused by the construction of the facility up to the time of the decision and, if the project is not approved, to restore it to its previous state.
The authorisation can be revoked at any time. Authorisation may be subject to conditions or subject to subsequent conditions. The competent authority may require the provision of a security to the extent necessary to ensure the fulfilment of its obligations as an applicant.
Competent office
Zuständig ist die Umweltabteilung des für den Anlagenstandort zuständigen Regierungspräsidiums.
Contact person
Regierungspräsidium Darmstadt - Dezernat IV / F 43.4 - Immissionsschutz (Metall)
Address
address
Opening hours
Das Regierungspräsidium ist montags bis donnerstags von 8 bis 16:30 Uhr und freitags von 8 bis 15 Uhr telefonisch erreichbar.
Bitte erkundigen Sie sich vor Ihrem Besuch über die Öffnungszeiten und ob eine Terminvereinbarung notwendig ist.
Contact
Regierungspräsidium Darmstadt - Dezernat IV / F 43.2 - Immissionsschutz (Chemie)
Address
address
Haltestellen
- Haltestelle: Hauptbahnhof, Südseite
Linien:- S-Bahn: Linie diverse Linien
- Bus: Linie diverse Linien
- Regionalbahn: Linie diverse Linien
- Straßenbahn: Linie diverse Linien
Opening hours
Das Regierungspräsidium ist montags bis donnerstags von 8 bis 16:30 Uhr und freitags von 8 bis 15 Uhr telefonisch erreichbar.
Bitte erkundigen Sie sich vor Ihrem Besuch über die Öffnungszeiten und ob eine Terminvereinbarung notwendig ist.
Contact
Regierungspräsidium Darmstadt - Dezernat IV / F 43.1 - Immissionsschutz (Energie, Lärmschutz)
Address
address
Haltestellen
- Haltestelle: Hauptbahnhof, Südseite
Linien:- S-Bahn: Linie diverse Linien
- Bus: Linie diverse Linien
- Regionalbahn: Linie diverse Linien
- Straßenbahn: Linie diverse Linien
Opening hours
Das Regierungspräsidium ist montags bis donnerstags von 8 bis 16:30 Uhr und freitags von 8 bis 15 Uhr telefonisch erreichbar.
Bitte erkundigen Sie sich vor Ihrem Besuch über die Öffnungszeiten und ob eine Terminvereinbarung notwendig ist.
Contact
Required documents
- Required drawings, plans, expert opinions
- Explanatory notes and
- other documents (please contact the competent authority if necessary).
Prerequisites
- The application you submit, as well as the required documents, must be able to adequately assess the impact of the planned plant.
- In addition, your application must show a legitimate interest in the early start.
- Furthermore, as an applicant, you must undertake to compensate for all damage caused by the premature construction up to the time of the decision and, if the project is not approved, to restore it to its previous state.
Basis for legal action
Legal remedy
- Contradiction
- Complaint
Procedure
- If you wish to obtain an authorisation to start the construction of a facility requiring a permit ahead of time, you must submit a written application in advance to the competent authority.
- Attach to the application the drawings, explanations and the justified choice of location required to check the requirements, as well as evidence of the need for an early start.
- The competent authority decides on the authorisation to start early.
- You will receive a notification of the granting or refusal of admission.
- In case of rejection, you can file an objection.
Deadlines
The application must be submitted before the construction of the plant begins.
Processing time
3 to 7 months (The authorisation procedure is part of the approval procedure, so the corresponding processing deadlines (with an extension option of three months) also apply.)
Costs
Fee from 625,00 EUR to 450.000,00 EUR
Notes (specifics)
In a procedure for the granting of a permit in the event of a significant modification of an installation requiring a permit, the licensing authority may, under certain conditions (pursuant to Section 16 (1) of the Federal Immission Control Act), also provisionally permit the operation of the plant.
A prerequisite for this is that the amendment fulfils an obligation arising from this Act or from an ordinance issued in connection with this Act.
Further Information
Area of validity
Hesse
Official approval
Officially approved by Saxon State Ministry of Energy, Climate Protection, Environment and Agriculture (SMEKUL) on 02.01.2024
Keywords
Vorläufige Errichtung Anlage, Zulassung vorzeitigen Beginns, Innerhalb Genehmigungsverfahren, Errichtung vor Genehmigungserteilung