Premature construction of a plant requiring approval in accordance with the BImSchG approval

    In a procedure for the granting of a permit for installations requiring a permit, you can submit an application to the competent authority for the early start of the construction of a plant.

    Description

    If you are seeking approval for the early construction of a facility requiring a permit, you must prove that:

    1. a decision in your favour can be expected,

    2. there is a public interest or a legitimate interest in the early start of their project, and

    3. You undertake to compensate for all damage caused by the construction of the facility up to the time of the decision and, if the project is not approved, to restore it to its previous state.

    The authorisation can be revoked at any time. Authorisation may be subject to conditions or subject to subsequent conditions. The competent authority may require the provision of a security to the extent necessary to ensure the fulfilment of its obligations as an applicant.

    Competent office

    Zuständig ist die Umweltabteilung des für den Anlagenstandort zuständigen Regierungspräsidiums.

    Contact person

    Regierungspräsidium Darmstadt - Dezernat IV / F 43.4 - Immissionsschutz (Metall)

    Address

    address

    Gutleutstraße 114

    60327 Frankfurt am Main

    Save contact

    Opening hours

    Das Regierungspräsidium ist montags bis donnerstags von 8 bis 16:30 Uhr und freitags von 8 bis 15 Uhr telefonisch erreichbar.

    Bitte erkundigen Sie sich vor Ihrem Besuch über die Öffnungszeiten und ob eine Terminvereinbarung notwendig ist.

    Contact

    telephone: +49 69 2714-5993

    fax: +49 69 2714-5906

    e-mail: Poststelle_IV_F@rpda.hessen.de

    Version

    Technisch geändert on 20.01.2025

    Language version

    de

    Sprache: de

    Regierungspräsidium Darmstadt - Dezernat IV / F 43.2 - Immissionsschutz (Chemie)

    Address

    address

    Gutleutstraße 114

    60327 Frankfurt am Main

    Save contact

    Haltestellen

    • Haltestelle: Hauptbahnhof, Südseite
      Linien:
      • S-Bahn: Linie diverse Linien
      • Bus: Linie diverse Linien
      • Regionalbahn: Linie diverse Linien
      • Straßenbahn: Linie diverse Linien

    Opening hours

    Das Regierungspräsidium ist montags bis donnerstags von 8 bis 16:30 Uhr und freitags von 8 bis 15 Uhr telefonisch erreichbar.

    Bitte erkundigen Sie sich vor Ihrem Besuch über die Öffnungszeiten und ob eine Terminvereinbarung notwendig ist.

    Contact

    Version

    Technisch geändert on 02.05.2025

    Language version

    de

    Sprache: de

    Regierungspräsidium Darmstadt - Dezernat IV / F 43.1 - Immissionsschutz (Energie, Lärmschutz)

    Address

    address

    Gutleutstraße 114

    60327 Frankfurt am Main

    Save contact

    Haltestellen

    • Haltestelle: Hauptbahnhof, Südseite
      Linien:
      • S-Bahn: Linie diverse Linien
      • Bus: Linie diverse Linien
      • Regionalbahn: Linie diverse Linien
      • Straßenbahn: Linie diverse Linien

    Opening hours

    Das Regierungspräsidium ist montags bis donnerstags von 8 bis 16:30 Uhr und freitags von 8 bis 15 Uhr telefonisch erreichbar.

    Bitte erkundigen Sie sich vor Ihrem Besuch über die Öffnungszeiten und ob eine Terminvereinbarung notwendig ist.

    Contact

    telephone: +49 69 2714-5990

    fax: +49 69 2714-5906

    e-mail: Poststelle_IV_F@rpda.hessen.de

    Version

    Technisch geändert on 02.05.2025

    Language version

    de

    Sprache: de

    Required documents

    • Required drawings, plans, expert opinions
    • Explanatory notes and
    • other documents (please contact the competent authority if necessary).

    Prerequisites

    • The application you submit, as well as the required documents, must be able to adequately assess the impact of the planned plant.
    • In addition, your application must show a legitimate interest in the early start.
    • Furthermore, as an applicant, you must undertake to compensate for all damage caused by the premature construction up to the time of the decision and, if the project is not approved, to restore it to its previous state.
    • Contradiction
    • Complaint

    Procedure

    • If you wish to obtain an authorisation to start the construction of a facility requiring a permit ahead of time, you must submit a written application in advance to the competent authority.
    • Attach to the application the drawings, explanations and the justified choice of location required to check the requirements, as well as evidence of the need for an early start.
    • The competent authority decides on the authorisation to start early.
    • You will receive a notification of the granting or refusal of admission.
    • In case of rejection, you can file an objection.

    Deadlines

    The application must be submitted before the construction of the plant begins.

    Processing time

    3 to 7 months (The authorisation procedure is part of the approval procedure, so the corresponding processing deadlines (with an extension option of three months) also apply.)

    Costs

    Fee from 625,00 EUR to 450.000,00 EUR

    Notes (specifics)

    In a procedure for the granting of a permit in the event of a significant modification of an installation requiring a permit, the licensing authority may, under certain conditions (pursuant to Section 16 (1) of the Federal Immission Control Act), also provisionally permit the operation of the plant.

    A prerequisite for this is that the amendment fulfils an obligation arising from this Act or from an ordinance issued in connection with this Act.

    Further Information

    Area of validity

    Hesse

    Official approval

    Officially approved by Saxon State Ministry of Energy, Climate Protection, Environment and Agriculture (SMEKUL) on 02.01.2024

    Version

    Technisch erstellt on 23.05.2023

    Technisch geändert on 14.05.2025

    Keywords

    Vorläufige Errichtung Anlage, Zulassung vorzeitigen Beginns, Innerhalb Genehmigungsverfahren, Errichtung vor Genehmigungserteilung

    Language version

    Deutsch

    Sprache: de

    Technisch erstellt on 07.06.2017

    Technisch geändert on 14.05.2025

    Englisch

    Sprache: en

    Sprachbezeichnung nativ:

    English

    Technisch erstellt on 07.07.2021

    Technisch geändert on 26.11.2019