Preliminary decision on a plant requiring a permit in accordance with the Federal Immission Control Act (BImSchG)
If you submit an application for a preliminary decision on an installation requiring a permit, the competent authority should approve it under certain conditions.
Description
After your application for a preliminary decision, the competent authority decides on individual approval requirements as well as on the location of the plant.
If the effects of the planned installation can be adequately assessed and there is a legitimate interest in issuing a preliminary decision, the competent authority should issue a preliminary decision. The preliminary decision becomes invalid if you have not applied for approval within two years.
Competent office
Zuständig ist die Umweltabteilung des für den Anlagenstandort zuständigen Regierungspräsidiums.
Contact person
Regierungspräsidium Darmstadt - Dezernat IV / F 43.4 - Immissionsschutz (Metall)
Address
address
Opening hours
Das Regierungspräsidium ist montags bis donnerstags von 8 bis 16:30 Uhr und freitags von 8 bis 15 Uhr telefonisch erreichbar.
Bitte erkundigen Sie sich vor Ihrem Besuch über die Öffnungszeiten und ob eine Terminvereinbarung notwendig ist.
Contact
Regierungspräsidium Darmstadt - Dezernat IV / F 43.2 - Immissionsschutz (Chemie)
Address
address
Haltestellen
- Haltestelle: Hauptbahnhof, Südseite
Linien:- S-Bahn: Linie diverse Linien
- Bus: Linie diverse Linien
- Regionalbahn: Linie diverse Linien
- Straßenbahn: Linie diverse Linien
Opening hours
Das Regierungspräsidium ist montags bis donnerstags von 8 bis 16:30 Uhr und freitags von 8 bis 15 Uhr telefonisch erreichbar.
Bitte erkundigen Sie sich vor Ihrem Besuch über die Öffnungszeiten und ob eine Terminvereinbarung notwendig ist.
Contact
Regierungspräsidium Darmstadt - Dezernat IV / F 43.1 - Immissionsschutz (Energie, Lärmschutz)
Address
address
Haltestellen
- Haltestelle: Hauptbahnhof, Südseite
Linien:- S-Bahn: Linie diverse Linien
- Bus: Linie diverse Linien
- Regionalbahn: Linie diverse Linien
- Straßenbahn: Linie diverse Linien
Opening hours
Das Regierungspräsidium ist montags bis donnerstags von 8 bis 16:30 Uhr und freitags von 8 bis 15 Uhr telefonisch erreichbar.
Bitte erkundigen Sie sich vor Ihrem Besuch über die Öffnungszeiten und ob eine Terminvereinbarung notwendig ist.
Contact
Required documents
- Required drawings, plans, expert opinions
- Explanations and
- other documents (if necessary, ask the competent authority).
Prerequisites
- From the application you have submitted, as well as the required documents, it must be possible to adequately assess the effects of the planned plant.
- In addition, your application must show a legitimate interest in the issuance of a preliminary decision.
- If a preliminary decision is issued, you must apply for approval within two years of the preliminary decision becoming final. The deadline may be extended to four years upon request.
Basis for legal action
Legal remedy
- Contradiction
- Complaint
Procedure
- If you would like to receive a preliminary decision on a plant requiring a permit, you must submit a written application in advance to the competent authority.
- The application must be accompanied by drawings, explanations and the justified choice of location required to check the prerequisites.
- The competent authority shall decide whether to issue the preliminary ruling.
- You will receive a decision on the granting or rejection of the preliminary decision.
- The preliminary decision becomes invalid if you do not apply for approval of the installation within two years. The deadline may be extended to four years upon request.
Deadlines
Period of validity: 2 years (The preliminary decision becomes invalid if you do not apply for approval of the installation within two years. In justified exceptional cases, the period of validity of the preliminary decision may be extended for up to two further years.)
Processing time
3 to 7 months (There is no legal deadline for the preliminary ruling procedure. The simplified approval procedure can be used as a guide. This is subject to a period of three months with a maximum of three months of extension.)
Costs
Es können weitere Kosten anfallen.: Fee from 600,00 EUR to 450.000,00 EUR
Further Information
Area of validity
Hesse
Official approval
Officially approved by Saxon State Ministry of Energy, Climate Protection, Environment and Agriculture (SMEKUL) on 02.01.2024
Keywords
Anlagenstandort, Voraussetzungen Genehmigung, Genehmigungsvoraussetzungen, Standort Anlage, Immissionsschutz, Vorbescheid zur Genehmigung, Standortwahl Anlage