Operation of an X-ray facility or significant change in operation Authorisation

    If you wish to operate technical X-ray equipment or make significant changes to it, you must first apply for a permit from the responsible radiation protection authority.

    Description

    You require a permit to operate or significantly change the operation of technical X-ray equipment that requires a permit. When you apply for this, the authorities will check the documents you have submitted. If all requirements are met, you will receive a permit.

    Contact person

    Unfortunately, no contact persons were found for Bad Vilbel (District Wetteraukreis, Hesse). Please check the service description above for information on how to find the responsible contact person.

    Required documents

    • Fully completed and signed application
    • Plans, drawings and descriptions required to check the approval requirements
    • Information that makes it possible to check whether
      • the number of radiation protection officers required for the safe performance of the activity has been appointed and that they have been granted the necessary powers to perform their duties,
      • it is ensured that the equipment is available and measures have been taken that are necessary according to the state of the art so that the protection regulations are complied with,
    • information that makes it possible to check whether the radiation protection officers are reliable and have the necessary expertise in radiation protection
    • a copy of a radiation protection instruction if it is necessary to issue a radiation protection instruction, i.e. in particular
      • Proof of expertise in radiation protection including proof of updating
      • Certificate and test report on radiation protection testing of the device by an expert or an expert organization
      • Type approval certificate with confirmation of routine testing or CE certificate of conformity
    • Proof of knowledge of radiation protection for the personnel deployed, including updates of this proof

    Prerequisites

    • There are no facts that raise concerns about the reliability of the person responsible for radiation protection or of the persons performing the tasks of the person responsible for radiation protection.
      • and: proof of specialist knowledge is available, if required.
    • The number of radiation protection officers required for the safe performance of the activity has been appointed and they have been granted the necessary powers to perform their duties.
    • It is ensured that the persons working have the necessary knowledge and skills with regard to possible radiation hazards and the protective measures to be applied.
    • The personnel required to carry out the work safely are available.
    • The equipment is available and the safety regulations are complied with.
    • This is a justified type of activity and there are no other public law regulations to the contrary.
    • Action before the administrative court

    Deadlines

    You must apply for approval before putting the X-ray equipment into operation.

    Processing time

    2 to 6 weeks

    Area of validity

    Hesse

    Official approval

    Officially approved by Federal Ministry for the Environment, Nature Conservation, Nuclear Safety and Consumer Protection (BMUV) on 31.01.2024

    Version

    Technisch erstellt on 22.05.2023

    Technisch geändert on 25.06.2024

    Keywords

    Betrieb einer Röntgeneinrichtung, Genehmigung, Genehmigungspflichtige Röntgeneinrichtungen, Röntgeneinrichtung, Änderung einer Röntgeneinrichtung, Technische Röntgeneinrichtung

    Language version

    Deutsch

    Sprache: de

    Technisch erstellt on 07.06.2017

    Technisch geändert on 14.05.2025

    Englisch

    Sprache: en

    Sprachbezeichnung nativ:

    English

    Technisch erstellt on 07.07.2021

    Technisch geändert on 26.11.2019