Report earth excavation

    Do you want to carry out drilling or other earthworks? Then you must notify the competent authority in advance.

    Description

    If you wish to carry out so-called earth excavations, you must notify the competent authority. Earth excavations are boreholes or other earthworks that reach so deep into the ground that they can affect the movement or quality of the groundwater. This can happen, for example, if soil layers are penetrated that protect the underlying groundwater from contamination.

    The notification must be made before you start work.

    Each borehole provides data for the assessment of the subsoil at the respective site. The notification enables the responsible authorities to gain an impression of the drilling project and the drilling material produced on site. The authorities can take additional measurements and ensure the quality of the drilling results. This prevents costly mistakes in underground spatial planning.

    The responsibility of the water authorities is determined by the location of the planned drilling points.

    Information for Wetteraukreis: Grundwasser

    Grundwasser

    Alle weiteren Informationen finden Sie unter dem angegebenen Link.

    Competent office

    The responsible authorities are determined by the location of the planned drilling points, usually the lower water authorities.

    Contact person

    Wetteraukreis - Wasser- und Bodenschutz

    Address

    postal address

    Post office box 10 06 61

    61146 Friedberg (Hessen)

    address

    Homburger Straße 17

    61169 Friedberg (Hessen)

    Save contact

    Elevator available

    Wheelchair access

    Opening hours

    Montag           07:30 – 12:30 Uhr, 13:30 – 16:00 Uhr

    Dienstag         07:30 – 12:30 Uhr, 13:30 – 16:00 Uhr

    Mittwoch        07:30 – 12:30 Uhr, 13:30 – 16:00 Uhr

    Donnerstag     07:30 – 12:30 Uhr, 13:30 – 16:00 Uhr

    Freitag            07:30 – 12:00 Uhr

    Contact

    telephone: 06031 83-4400

    fax: 06031 83-914400

    e-mail: wasserbehoerde@wetteraukreis.de

    Internet

    Keywords

    Bodenschutzbehörde, Immissionsschutzbehörde, Untere Wasserbehörde

    Version

    Technisch geändert on 09.05.2025

    Language version

    de

    Sprache: de

    Contradiction

    Procedure

    If your request is a notification, you may start your project if you have not heard from the authorities within one month
    If your project requires approval, exemption or authorization under water law, you will receive a response within one month.

    Deadlines

    The notification must be made before you start work.

    Area of validity

    Hesse

    Official approval

    Officially approved by Hessian Ministry for the Environment, Climate Protection, Agriculture and Consumer Protection on 29.03.2023

    Version

    Technisch erstellt on 07.02.2023

    Technisch geändert on 08.07.2024

    Keywords

    Baugrunduntersuchung, Baugrundsondierung, Rohstoffe, Altbergbauerkundung, Erdarbeiten, Geophysikalische Untersuchung, Kellerbau, Altlastenerkundung, Bauvorhaben, Pfahlgründung, Hohlraumerkundung, Erdaufschluss, Bohrung, Grundwassermessstelle, Kartierung, Brunnen, Grundwasser, Bohranzeige, Ingenieurgeologische Untersuchung, Bodeneingriff

    Language version

    Deutsch

    Sprache: de

    Technisch erstellt on 07.06.2017

    Technisch geändert on 14.05.2025

    Englisch

    Sprache: en

    Sprachbezeichnung nativ:

    English

    Technisch erstellt on 07.07.2021

    Technisch geändert on 26.11.2019