Indication of blasts
Für eine Sprengung ist eine vorherige Anzeige abzugeben.
Description
Before blasting with explosive substances, the holder of the permit according to § 7 of the Explosives Act must notify the competent authority of the blast (e.g. in the case of a building explosion or in the case of blasting in the course of road construction measures).
Note: Blasting in facilities that are approved in accordance with § 4 of the Federal Immission Control Act (e.g. in quarries) is exempt from the notification obligation. However, this only applies to blasting, which is included in the permit.
Online services
There is currently no online service available for this location.
Contact point
The respective regulatory authority of the city or municipality is responsible for receiving the notification.
The latter forwards a copy of the notification to the relevant regional council.
The enforcement departments for occupational health and safety technology at the regional councils of Darmstadt, Giessen and Kassel are responsible for monitoring the execution of the blasting work.
You can also complete the procedure electronically via the Point of Single Contact
Contact person
Unfortunately, no contact persons were found for Bad Vilbel (District Wetteraukreis, Hesse). Please check the service description above for information on how to find the responsible contact person.
Required documents
Completed notification form with any necessary plans and calculation documents.
Forms
A separate platform has been developed for online applications. On the so-called service platform, you can submit your applications electronically and much more! You are welcome to get your own impression of the application in advance without registering beforehand. To do this, use the simulation. In order to take full advantage of the online application process, you must first register with the online application process.
- Online application process(Point of Single Contact Hesse)
Prerequisites
- Sie benötigen eine Erlaubnis nach § 7 des Sprengstoffgesetzes (SprengG).
- Sofern die Erlaubnis die Fachkunde nicht enthält, benötigen sie zusätzlich den Befähigungsschein nach § 20 SprengG
- Da insbesondere der Befähigungsschein befristet ist, muss dieser am Tag der Sprengung gültig sein
- Die Sprengarbeiten, die ausgeführt werden sollen, müssen im Befähigungsschein aufgeführt sein
Basis for legal action
Procedure
The notification must be made in writing in duplicate. The notification must contain all the information specified in § 1 of the 3rd Ordinance on the Law on Explosives.
If, after the notification has been filed, changes have occurred in relation to the content of the notification, a notification of change must also be made in duplicate.
Deadlines
Application deadline: 1 week (vor der Sprengung)
Application deadline: 4 weeks (vor mehreren gleichartigen Sprengungen)
Costs
There are no fees or costs.
Notes (specifics)
Für die Kontrolle und Überwachung von Sprengungen sind in Hessen die Regierungspräsidien zuständig.
Further Information
Area of validity
Hesse
Official approval
Officially approved by Hessisches Ministerium für Arbeit, Integration, Jugend und Soziales on 01.02.2024
Keywords
Dritte Verordnung zum Sprengstoffgesetz, SprengG, Sprengstoff, Explosionsgefährliche Stoffe, Sprengung, Abbruchsprengung, Gewinnungssprengung, Anzeige, Sprengstoffgesetz, Steinbruch, Gesteinssprengstoff, § 1 3 SprengV, 3 SprengV, explosionsgefährliche Stoffe