Applying for planning approval for operating facilities of the federal railroads

    If you wish to build, modify or dismantle a federal railroad operating facility, you must apply to the Federal Railway Authority (EBA).

    Description

    If you are planning to build, modify or dismantle railroad operating facilities, you must apply for the relevant permit from the Federal Railway Authority (EBA). The operating facilities include in particular

    • Rail tracks
    • Engineering structures such as bridges, tunnels, culverts
    • Earthworks such as embankments, cuttings, embankments
    • Signaling, safety and telecommunications systems
    • Railroad stations and stops

    Before the construction, modification or dismantling of such a facility, questions must be clarified in the planning procedure, in particular

    • Is the project technically feasible?
    • Does the planning comply with the applicable regulations and safety standards?
    • Is an environmental impact assessment required for the project - and if so, what is the result of the environmental impact assessment?
    • Does the project affect public interests?
    • Does the project affect the rights or interests of third parties?
    • Can the rights of third parties and the public and private interests be fairly balanced?

    On this basis, the EBA decides whether the plans for the construction, modification or dismantling of a railroad operating facility are permissible and whether your application can be approved.

    The German Bundestag can approve transport infrastructure projects by means of a Measures Act instead of a planning approval decision. A preparatory procedure for approval is carried out before the legislative procedure is initiated. You can apply to the EBA for this.

    Online service

    Antrags- und Beteiligungsportal für Verkehr und Offshore-Vorhaben

    ID: B100019_106732600

    Description

    Im Antrags- und Beteiligungsportal für Verkehr und Offshore-Vorhaben des Bundes können Sie Anträge auf Durchführung von Planrechtsverfahren der Verkehrsträger Wasserstraße, Fernstraße und Schiene sowie zu Offshore-Vorhaben stellen. Sie können Stellungnahmen und Einwendungen zu Planrechtsverfahren der Verkehrsträger Wasserstraße, Fernstraße (sofern das Fernstraßen-Bundesamt das Verfahren durchführt) und Schiene sowie zu Offshore-Vorhaben einreichen.

    Use this service online

    Payment methods

    • SEPA transfer

    Trust level

    You need an Elster certificate with password to use this online service (trust level: substantial).

    further information on the level of trust for online services

    Identification

    • electronic identification using national eID means – software certificate

    Language

    Deutsch

    Sprache: de

    Contact person

    Eisenbahn-Bundesamt (EBA) - Außenstellen - Sachbereiche 1

    Opening hours

    Nach Vereinbarung

    Internet

    Payment methods

    The following payment method is possible: SEPA transfer

    Version

    Technisch geändert on 17.02.2023

    Language version

    Deutsch

    Sprache: de

    Required documents

    • Initial application for the issue of a planning permission decision or an application to amend an existing planning permission decision
    • Initial application for the implementation of a preparatory procedure or application for the adoption of additional regulations by the authority
    • Explanatory report
    • General maps and plans
    • Site plans
    • List of structures and plans
    • Land acquisition register and plans
    • Site layout and development plans
    • Landscape conservation plan
    • If necessary, further evidence according to the EBA application documents guidelines

    Forms

    Forms available: Yes
    Written form required: Yes
    Informal application possible: No
    Personal appearance necessary: No

    Online services available: Yes

    Prerequisites

    Applications can only be submitted by the federal railroads.

    • Objection to plan waiver
    • Action before the administrative court against planning approval decision and planning approval

    Procedure

    You can submit your application for a planning approval procedure by post or online.

    Apply for planning permission by post:

    • Download the form "Antrag auf Erteilung einer planungsrechtlichen Zulassungsentscheidung" or the application form "Vorbereitendes Verfahren nach MgvG mit Beiblatt" from the website of the Federal Railway Authority.
    • Complete the application in full and sign it.
    • Attach all the necessary documents. You will find a description of the planning documents that you must attach to your application in the Guidelines on Application Documents, the Planning Approval Directive and the EBA's Environmental Guidelines.
    • Send the application and the documents to the EBA branch office responsible for the location of the construction project.
    • The EBA will check your documents and, if necessary, contact you if further submissions are required.
    • If a hearing procedure is to be carried out, you must respond to the comments submitted and objections received as part of the official and public participation process. If a hearing takes place, you must attend it.
    • You will receive a notification by post or by handing it over to the authority in which the decision on the planning approval decision is communicated.
    • You will also receive a notification of fees by post.
    • You pay the fees.

    Apply for planning permission online:

    • Go to the website of the federal portal verwaltung.bund.de. From there you will be redirected to the federal planning portal. Alternatively, you can access it directly from your browser.
    • Log in to your ELSTER company account with your ELSTER certificate.
    • The form management system (FMS) will guide you step by step through the required information. Complete the application form in full.
    • Upload the required documents as a file. You will find a description of the planning documents that you must attach to your application in the Application documents guide, the Planning Approval Directive and the EBA's environmental guidelines.
    • Send the application and the documents to the EBA branch office responsible for the location of the construction project.
    • You will receive an automatic confirmation of receipt.
    • The remaining procedural steps correspond to the written procedure.
    • Instead of being sent by post or delivered to the authority, you can be notified of the decision on the planning approval via the ELSTER company account.
    • Instead of being sent by post, you can be notified of the fee notice via the ELSTER business account.

    Deadlines

    There is no deadline for submitting an application. Individual deadlines may be imposed by the authorities for subsequent submissions or responses.

    Objection deadline: 1 month (Ein Widerspruch ist nur gegen den Planverzicht möglich. Die Widerspruchsfrist beginnt mit Bekanntgabe des Verwaltungsaktes gegenüber der Beschwerten beziehungsweise dem Beschwerten.)

    Processing time

    3 to 4 years (Die Dauer des behördlichen Verfahrens ist abhängig vom Einzelfall, von der Art und des Umfangs des Vorhabens und der Qualität der Planunterlagen. Auch wird sie durch gesetzliche Verfahrensvorschriften beeinflusst. Sie kann im Einzelfall länger als 4 Jahre dauern.)

    Costs

    Die Höhe der Gebühren richtet sich nach der Besonderen Gebührenverordnung Eisenbahn-Bundesamt (EBABGebV). Entweder handelt es sich um eine Festgebühr oder die Höhe bemisst nach Zeitaufwand oder ist abhängig von den Baukosten des Vorhabens.: Fee from 2.900,00 EUR to 4.205.900,00 EUR (Information on cost composition can be found here)

    Notes (specifics)

    The type of procedure carried out can be changed by the authorities during the ongoing process.

    Further Information

    Area of validity

    Germany-wide

    Official approval

    Officially approved by Federal Ministry for Digital and Transport Affairs (BMDV) on 07.02.2023

    Version

    Technisch geändert on 10.03.2026

    Keywords

    Dismantling the railroad operating facility, Application for railroad operating facility, Planning approval, Application to the Federal Railway Authority, Change railroad operating system, Federal Railway Authority branch office, Application according to MgvG, Preparatory procedure MgvG, Planning approval procedure, Plan approval, Federal Railway Authority, Building a railroad operating facility