Show installation and decommissioning of publicly accessible charging points

    If you put publicly accessible normal and fast charging points into or out of operation, you must notify the Federal Network Agency. You must also notify the Agency if you make private charging points public or hand over your charging points to another operator.

    Description

    If you put publicly accessible normal and fast charging points for electric vehicles into operation or take them out of operation, you must notify the Federal Network Agency. You must also notify the Federal Network Agency if you make private charging points public or hand over your publicly accessible charging points to another operator.

    The obligation to notify applies to all normal charging points that were put into operation after 17.03.2016 and to all fast charging points.

    Normal charging points have a maximum charging capacity of 22 kilowatts.
    Fast charging points have a charging capacity of more than 22 kilowatts.

    A charging point is publicly accessible if it is located either on a public road or on private land and the parking space belonging to the charging point can be used by others.

    Online service

    Reporting portal of the Federal Network Agency (BNetzA) for the charging station register

    ID: B100019_116821672

    Description

    The reporting portal of the Federal Network Agency (BNetzA) for the charging station register offers you the opportunity to fulfill your reporting obligations for publicly accessible charging points for electric vehicles online.

    Use this service online

    Trust level

    You need an account with password to use this online service (trust level: basic registration).

    further information on the level of trust for online services

    Identification

    • no identification

    Language

    Deutsch

    Sprache: de

    Englisch

    Sprache: en

    Sprachbezeichnung nativ:

    English

    Contact person

    Bundesnetzagentur für Elektrizität, Gas, Telekommunikation, Post und Eisenbahnen (BNetzA) - Referat 620 - Ladepunktanzeige

    Address

    address

    Tulpenfeld 4

    53113 Bonn

    Save contact

    Opening hours

    Montag: 09:00 bis 16:00 Uhr Dienstag: 09:00 bis 16:00 Uhr Mittwoch: 09:00 bis 16:00 Uhr Donnerstag: 09:00 bis 16:00 Uhr Freitag: 09:00 Uhr bis 15:00 Uhr

    Contact

    Internet

    Version

    Technisch geändert on 14.10.2024

    Language version

    Deutsch

    Sprache: de

    Required documents

    Operators of fast-charging points must also provide evidence of compliance with the technical requirements of the ordinance by enclosing a commissioning report signed by a qualified electrician.

    Prerequisites

    You are planning to install a publicly accessible charging point for electric vehicles or are already operating publicly accessible normal or fast charging points.

    As this is a notification procedure, no administrative decisions are made against which an appeal could be lodged.

    Procedure

    You can submit the notification using the online form.

    Notification of installation or decommissioning:

    • Register on the reporting portal for the charging station register or log into your existing account.
    • Open the online form for reporting a publicly accessible charging station in the reporting portal.
    • Complete the online form and upload the required documents.
    • Submit the form electronically.
    • The Federal Network Agency will check your notification and send you a query in the portal or confirm your details.
    • The Federal Network Agency will publish the charging points on its website once the notification is complete and has been confirmed.

    Notification of a change of operator:

    • Log into your existing operator account in the reporting portal for the charging station register.
    • In your table overview, select the charging stations to be displayed for an operator change.
    • Define the future operator by entering their operator ID and the time of the operator change.
    • Send the notification of the operator change.
    • The new operator must confirm the notification in their operator account.

    Deadlines

    • Notification period up to 2 weeks after commissioning
    • Decommissioning must be reported immediately

    Application deadline: 2 weeks

    Processing time

    1 to 2 days

    Costs

    There are no costs for you.

    Further Information

    Area of validity

    Germany-wide

    Official approval

    Officially approved by Federal Ministry of Economics and Climate Protection (BMWK) on 11.10.2024

    Version

    Technisch geändert on 01.12.2025

    Keywords

    E-car

    Language version

    Deutsch

    Sprache: de

    Englisch

    Sprache: en

    Sprachbezeichnung nativ:

    English