Submit a declaration of compliance with the requirements of the Building Energy Act for changes to existing buildings

    If you own a heated or cooled building and you are renewing, replacing or installing external components for the first time and the building is assessed for energy efficiency, you must prove that the building complies with the energy requirements of the Building Energy Act.

    Description

    The Building Energy Act sets requirements for the energy performance of buildings. The owner of a heated or cooled building must prove that the building meets the requirements of the Building Energy Act. Proof is provided with the declaration of compliance. The declaration of compliance must be submitted after external components of the building have been renewed, replaced or installed for the first time and the building has been assessed in terms of energy efficiency.

    Competent office

    Lower building supervisory authority

    Lower building supervisory authority

    Information for Hesse: Erfüllungserklärung für die Einhaltung der Anforderungen des Gebäudeenergiegesetzes bei Änderungen von bestehenden Gebäuden einreichen

    Lower building supervisory authority

    Contact person

    Please enter a location or postcode in the City / Location input field to see the responsible contact person

    Required documents

    • Declaration of fulfillment
    • Energy certificate[s]
    • Calculations
    • if applicable
      • Contractor's declaration
      • Supplier confirmation
      • Supplier certificate
      • Notification of exemption from the requirements of the Building Energy Act
    • The energy certificate must refer to the completed building.

    Information for Hesse: Erfüllungserklärung für die Einhaltung der Anforderungen des Gebäudeenergiegesetzes bei Änderungen von bestehenden Gebäuden einreichen

    • The energy certificate must refer to the completed building.

    Forms

    • Personal appearance required: No

    Prerequisites

    They must confirm that the requirements of the Building Energy Act are met.

    No legal remedy is possible.

    Procedure

    The respective countries regulate the procedure for the declaration of compliance, the authorization to issue it, the mandatory information and the evidence to be submitted.

    Deadlines

    • Submission of the declaration of compliance after completion of the measure
    • The declaration of fulfillment must be submitted upon completion of the work.

    Information for Hesse: Erfüllungserklärung für die Einhaltung der Anforderungen des Gebäudeenergiegesetzes bei Änderungen von bestehenden Gebäuden einreichen

    • The declaration of fulfillment must be submitted upon completion of the work.

    Area of validity

    Hesse

    Official approval

    Officially approved by Hessian Ministry of Economics, Energy, Transport, Housing and Rural Areas on 03.07.2024

    Version

    Technisch erstellt on 24.05.2024

    Technisch geändert on 26.02.2025

    Language version

    Deutsch

    Sprache: de

    Technisch erstellt on 07.06.2017

    Technisch geändert on 14.05.2025

    Englisch

    Sprache: en

    Sprachbezeichnung nativ:

    English

    Technisch erstellt on 07.07.2021

    Technisch geändert on 26.11.2019