Construction and operation of a system requiring monitoring in accordance with the Industrial Safety Ordinance Permit for gas filling systems

    If you wish to set up or operate a gas filling system or make certain changes to it, you must apply for a permit from the competent authority.

    Description

    Gas filling systems, including storage and storage tanks, are used to fill land, water and air vehicles with flammable gases, which are then used as propellant or fuel. Gas filling systems are systems that require monitoring.
    You require a permit from the competent authority if you:

    • wish to set up and operate a gas filling system
    • wish to make changes to the design or mode of operation that affect safety

    Permission can be granted subject to the following restrictions:

    • limited,
    • limited in time,
    • subject to conditions or
    • with conditions.

    If the installation requiring a permit is part of an installation requiring a permit, no separate permit will be issued. The authorization includes the permit.

    Competent office

    The occupational health and safety departments of the Darmstadt, Giessen and Kassel regional councils are responsible.

    Contact person

    Please enter a location or postcode in the City / Location input field to see the responsible contact person

    Required documents

    Informal application with the following details:

    • Surname, first name, company name
    • Address of the applicant
    • Contact information (e-mail, telephone, fax)
    • Type of permit
      • Construction and operation
      • Modification and operation or
      • Partial permit
    • Specification of the operating site

    Documents required to assess the installation:

    • Subject of the application
    • Description of the installation
    • Description of the plant technology and interaction with other plants
    • Piping and instrumentation flow diagram (P&I flow diagram)
    • Safety data sheets
    • Description of mode of operation
    • Permanently manned position for operation without supervision
    • Overview plan
    • Site plan
    • Floor plan/technical plan
    • Ex-zone plan
    • Explosion protection concept
    • Information on fire protection
    • Calculation of production costs
    • Other installations
    • Test report from an approved inspection body (ZÜS)
    • The test report must confirm that the system can be operated safely if the specified measures are complied with

    Forms

    Forms available: No

    Written form required: Yes

    Informal application possible: Yes

    Personal appearance necessary: No

    Online services available: No

    Prerequisites

    • The facility for which you are applying for a permit must be a facility requiring a permit.
    • You must construct and operate filling stations in accordance with the state of the art.
    • Your documentation must be complete, plausible and meaningful.
    • The test report from the approved inspection body (ZÜS) must confirm that the system applied for can be operated safely if the measures specified in the documents, including the tests, are complied with.

    Appeal:

    • You can appeal against the decision within one month of notification.
    • You must submit the appeal to the competent authority in writing or for the record.

    Procedure

    • Submit the application for approval of the system requiring monitoring with the required documents including the test report from the approved monitoring body (ZÜS) to the responsible authority.
    • If a permit is required in accordance with the Federal Immission Control Act, you will receive the application documents back, as a permit in accordance with the Industrial Safety Ordinance will then also be checked as part of the necessary permit in accordance with the Federal Immission Control Act.
    • The competent authority will make its decision after examination and inform you.

    Deadlines

    The permit expires if:

    • you have not commenced construction of the installation within two years of the permit being issued,
    • you have interrupted the construction of the installation for two years or longer or
    • you have not operated the installation for a period of three years.

    You can apply to the licensing authority for an extension of the deadlines for important reasons.

    Processing time

    0 to 3 months (The processing time applies from receipt of the complete application documents. An extension of the processing period is possible in justified cases.)

    Costs

    Administrative fees are charged in accordance with the applicable administrative cost regulations.

    Further Information

    The publication (LV 49) contains a list of the required application documents for gas filling systems in Annex 3.

    Area of validity

    Hesse

    Official approval

    Officially approved by Hessian Ministry for Social Affairs and Integration (HMSI) on 11.07.2023

    Version

    Technisch erstellt on 23.05.2023

    Technisch geändert on 26.02.2025

    Keywords

    LNG, Bau, erlaubnisbedürftige Anlagen, Montage, Gastankstelle, Befüllen von Fahrzeugen, Wasserstoff, Arbeitssicherheit, Anlagen mit Druckgeräten, Erdgas, Gasfüllanlage, LPG, Flüssiggas, Änderungen der Betriebsweise, Vorratsbehälter, Änderungen der Bauart, erlaubnispflichtige Anlagen, Genehmigung, Installation, Lagerbehälter

    Language version

    Deutsch

    Sprache: de

    Technisch erstellt on 07.06.2017

    Technisch geändert on 14.05.2025

    Englisch

    Sprache: en

    Sprachbezeichnung nativ:

    English

    Technisch erstellt on 07.07.2021

    Technisch geändert on 26.11.2019